挑战
PEDG faced several challenges while planning the 2012 iHeartRadio event at the MGM Grand in Las Vegas. The logistics of accommodating 22 world-famous musicians and improving upon the previous year's show with a similar budget were significant hurdles. Additionally, the team lost three installation days due to a tight timeline, which didn't allow enough time to scale the show. The team had to ensure that every detail was perfect to avoid delays, as a single misstep could back up the entire project. They also had to contend with discrepancies in the initial AutoCAD drawings provided by the MGM Grand, which required them to travel to the site to measure it themselves.
关于客户
Performance Environment Design Group LLC (PEDG) is a scenic and lighting design company known for its transformational designs and industry accolades, including the Telly Award, Eddie Award, and Tour Link Top Dog Award for lighting design. With offices in Lancaster, Pennsylvania, and Los Angeles, PEDG has worked on high-profile events such as the NHL Winter Classic, Pepsi Fan Jam, MTV’s Iggy Awards, and A-list concerts. Their attention to detail and quality work have made them a go-to choice for clients like the iHeartRadio Music Festival and the NFL Kickoff event. PEDG's designs are known for their powerful, artful landscapes of light, fabric, video, and sound, delighting and inspiring audiences.
解决方案
PEDG used Vectorworks Designer software, along with a few other applications, to coordinate the artists' needs and find cost-saving measures to meet the budget. The team spent a lot of time in the CAD program ironing out details to ensure everything fit perfectly. They began with AutoCAD drawings from the MGM Grand but had to create accurate drawings in Vectorworks after finding discrepancies. The program helped them manage all aspects of production, including occupancies, scenic, audio, and video elements. PEDG produced detailed drawings to communicate requirements and quantify components, ensuring everything was calculated down to the last detail. This meticulous planning allowed them to build the iHeartRadio set in three days, rehearse on the fourth day, and hold concerts on the fifth and sixth days.
运营影响
  • PEDG generated all documents for the crews helping to build and set up the festival, ensuring smooth setup and accurate measurements.
  • The use of Vectorworks software allowed the team to visualize the space in advance, identify obstacles, and produce accurate symbols.
  • The team designed complex rigging with over 200 motors, using Vectorworks to calculate materials, elevation, cable length, and point weight.
数量效益
  • The iHeartRadio set was built in three days, with rehearsals on the fourth day and concerts on the fifth and sixth days.
  • The team lost three installation days but still managed to complete the setup on time.
  • The project involved more than 200 motors running the show, all meticulously planned and calculated using Vectorworks software.

相关案例.

联系我们

欢迎与我们交流!

* Required
* Required
* Required
* Invalid email address
提交此表单,即表示您同意 IoT ONE 可以与您联系并分享洞察和营销信息。
不,谢谢,我不想收到来自 IoT ONE 的任何营销电子邮件。
提交

Thank you for your message!
We will contact you soon.